Electricity

Barrier index per category and technology

Heating and Cooling

Barrier index per category and technology

Transport

Barrier index per category and technology

Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In the former feed-in tariff system (KÁT), which was in place until December 2016, tariffs were only partly differentiated by technologies (only wind and sun). Within the new scheme METÁR, which is in force from January 2017, there is no real technological differentiation as well – tariffs are only different for PV. Technological differentiation is rather done by setting the support period. Although there are benchmark periods for almost all technologies, the eligibility period for feed-in or premium support is set project-by-project thus reducing investors’ visibility. In addition, feed-in tariffs and market premiums are too low for many technologies without other support (i.e. investment grant). However, not every technology is considered within the decree on benchmark periods for the feed-in tariff or the market premium (only biomass, biogas, photovoltaic and organic waste).

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: HUE01
Category: Political and economic framework
Sub-Category: Remuneration level for RES
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The Hungarian remuneration scheme for renewable electricity has been planned to be reformed since 2011. The first planned introduction date of the new, revised tariff system (Megújuló Villamos Energia Támogatási Rendszer - METÁR) was 1 January 2012, then early 2013. However, the content of the reform has been accepted by the Hungarian parliament only in June 2016. The final version of METÁR was introduced from January 2017 and comprises the feed-in tariff scheme, market premium scheme and tendering procedures. This uncertainty about the remuneration scheme reform has had a negative effect on RES investments and the trust in the new system is missing due to the fact that e.g. no tenders have been introduced yet.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: HUE02
Category: Political and economic framework
Sub-Category: Existence of RES support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There are some state funded soft loan programs in Hungary, partially realised with EU funds. However, these programs are not standardized leading to high uncertainty among project developers and other stakeholders like producers and installers. Moreover, the funds are mainly accessible within tendering procedures only, which are considered being non-transparent. For some technologies, there are no funds (e.g. soft loans) available at all, foremost for wind energy.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE03
Category: Political and economic framework
Sub-Category: Access to finance
Affected Technologies:
Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In the past, the MOL company received backup support for drilling risks from the International Finance Corporation’s (IFC) infrastructural crisis facility (guarantee to pay 85% of costs of unsuccessful geothermal exploration wells). However, there is no stable, state financed insurance scheme to cover drilling risks of geothermal projects which hampers the roll-out of geothermal power generation (as this would need deeper drilling to tap high temperature reservoirs).

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE04
Category: Political and economic framework
Sub-Category: Access to finance
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In Hungary, the complexity of administrative procedure depends on the size of a RES plant. The ordinances define three categories of electricity generating installations/utilities: Category 1 – small-scale residential RES installations (up to 50 kW), Category 2 - small plants not subject to authorization (50-500 kW), and Category 3 - RES plants which require a power producer’s operating license (exceeding 500 kW). Operators of plants belonging to Category 2 and 3, are eligible for the feed-in premium (up to 1 MW) or tendering procedures. For Category 1, net-metering applies. In addition, for plants with the capacity higher than 500 kW (Category 3) the operators have to hand in a schedule for electricity production on a daily basis. The strict scheduling system is associated with a high administrative burden and along with the high number of authorities involved is one of the main reasons why the investors decide against the construction of a plant with a capacity higher than 500 kW.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE06
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Present condition of grid infrastructure allows integration of only a very limited intermittent capacity. According to the National Renewable Action Plan for 2020, an additional 410 MW wind capacity could be integrated at present grid condition. Nevertheless, there are no concrete plans for the integration of RES in electricity sector in general. Moreover, the development of the grid is considered insufficient and barely no investments have been made in the past.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: HUE07
Category: Grid regulation and infrastructure
Sub-Category: Transparent and foreseeable grid development
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

RES generators have an information disadvantage against DSOs as they do not know the possible connection points. As the connection request is free of charge for the RES generator and the DSO is obliged to reply to it, it often happens that the investor only wants to get information from the DSO, without any concrete plans to build a RES plant (so called ‘paper RES-E plants’). It takes time for a DSO to address the requests of these so called ‘paper RES-E plants’, which as a result may hamper the development of ‘real’ RES-E projects.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: HUE09
Category: Grid regulation and infrastructure
Sub-Category: Predictability / transparency of connection procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The DSOs have a strong position in Hungary when it comes to the connection of new RES-E plants to the distribution grid (especially installations with a capacity >50 kW). Although the project developer has to pay a certain grid connection fee, this amount is not sufficient to incentivise the grid expansion by the DSO. In most instances, the result is that the grid extension costs are passed on to the project developer. This creates a high rate of exclusivity for urban regions and large enterprises, since they have better financial and infrastructural opportunities. On the other hand, the projects of small and medium-sized enterprises are often impeded due to the strong position of the DSO, especially when no investment funding is given. Furthermore, the six DSOs who are responsible for maintenance and expansion in a certain region of Hungary do not have harmonized statutes which also contributes to asymmetries between the areas of responsibility and enhances uncertainty for the system installer.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: HUE10
Category: Grid regulation and infrastructure
Sub-Category: Lack of infrastructure and infrastructure development
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There are little incentives for DSOs for fast connection of RES plants. This is partly because it is deemed that RES technologies with volatile electricity production (e.g. wind or solar power) are difficult to integrate and that the effort is not shared equally. The latter is owed to the fact that household-sized installations up to 50 kW do not have to pay system use charges and profit from the net-metering regulation at the same time. However, the regulatory authority - Hungarian Energy and Utility Regulatory Authority (HEA) - introduced a decree which foresees system usage fees for installations >4 kW. Currently, the fee is set at 0 HUF but might be raised in the near future.

Sector(s): Electricity
Code: HUE11
Category: Grid regulation and infrastructure
Sub-Category: Duration of RES grid access
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There is a so called (semi-)deep approach regarding the grid connection costs. According to the Hungarian legislation RES-E generators pay also part of the grid reinforcement costs. 50% reduction in connection charges is possible, however RES plants not often make use of it as it can be less costly for them to make the needed investment themselves. The reduction of the connection charges is taken into account as support when setting the length of the feed-in period.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: HUE12
Category: Grid regulation and infrastructure
Sub-Category: Cost of RES grid access
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In Hungary, the licensing procedure may involve a great number of authorities, which makes the administrative procedure more complex. For small plants (up to 50-500 kW), approx. 9 authorities are involved in the construction and authorization process which also depends on the ownership structure of the selected site. If the site has to be acquired, the amount of the authorities involved might rise to 13. Before the ban for the construction of new plants in September 2016 (memorandum of 2016), the number of the authorities involved for Onshore power projects rose to approx. 30 and the number of licenses required for construction and authorization has tripled in the past years. Hypothetically, this might result in an authorization process lasting for 3-4 years. When it comes to PV, the administrative process takes approx. 4-6 month for the plants between 50-500 kW. Concerning PV installations exceeding 500 kW, which require power producer’s operating license, the authorization/construction process might take up to 2 years. According to the stakeholders, the environmental authority has made the authorization process more difficult in the past three years.

Sector(s): Electricity
Code: HUE13
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Given the fact that competent authorities can involve into the licensing procedure many other so called professional authorities (like the state chief architect, fire safety agencies, cultural heritage administration, etc.) and these administrative procedures are not affected by the deadline of the main competent authority, the whole process can take more time than actually foreseen by laws.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: HUE14
Category: Administrative processes
Sub-Category: Duration of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

As cost of administrative procedures can be a direct financing tool for authorities, they have an interest in starting more administrative procedures. This, however, results in some extra costs for investors. According to investors, the administrative cost of authorization procedures rather increased than dropped in the past years. Furthermore, the cost may vary according to the stakeholders involved, because the authorisation procedure is not standardized and therefore not transparent.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE15
Category: Administrative processes
Sub-Category: Cost of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The RES benefits are mostly indirect but the support cost of RES-E has a direct and immediate effect on energy bills, which is also a politically sensitive issue in Hungary. Households do not have to bare the costs of the Hungarian feed-in tariff directly, since they are the beneficiaries of the so called ‘universal service’. The universal service is a system of regulated energy prices for private consumers in Hungary. For example, utilities are neither allowed to pass on certain costs (e.g.) to households, nor are costs for RES schemes integrated in their bills. In consequence, the government passes on the costs for the financial support of RES-E to enterprises. On the other hand, the companies also benefit from artificially low electricity prices. Therefore, the tax payers will pay the costs of the support scheme anyway, which they are aware of. In addition, benefits of RES are not obvious to the general public which might be an explanation to missing public support for RES.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE16
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Biomass
RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In order to receive FIT support for the electricity generations wood has to meet certain sustainability criteria. Thus, only wood from sustainable forestry and lower quality wood can be supported with a feed-in tariff. In addition, the biomass (= here: foodstuff) used for electricity generation cannot be appropriate for human alimentation (priority use) and has to be in line with the EU Timber Regulation (995/2010) in order to receive the feed-in tariff.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: HUE17
Category: Other
Sub-Category: Sustainability criteria for biomass
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The lack of training in the field of RES-E technologies may hamper the efficient operation of RES-E plants. It refers to vocational and academic training and is especially affecting small producers. Positive developments regarding this matter included trainings in the field of energy efficiency and renewable energy technologies within the frame of the IEE “BUILD UP Skills TRAINBUD” programme. Also in line with the educational programme “LEONARDO Innovation Transfer Programme” and its corresponding sub-programme called “SEE-REUSE” (Strengthening European Education in Renewable Energy Utilization for Sustainable Economy), best practice RES-training programmes (in particular Austrian/German) are planned to be adapted to the Hungarian Qualification Register.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE18
Category: Other
Sub-Category: Training
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The lack of transparent information from authorities regarding licensing procedures of RES-E plants causes uncertainties not only for investors but also for administrators in the respective competent authorities. Also, standardised application forms are not available in many cases.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: HUE19
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The government’s RES-E strategy may appear inconsistent when it comes to the extension of the Paks nuclear power plant, which should be extended by two new 1200 MW-reactors. Hungary’s only operating nuclear power station in the country currently accounts for over 40% of the country’s electricity production. In the long run, this development will hamper the development of renewables in the electricity sector, since infrastructure and market system requirements of nuclear power and a growing share of renewables differ very much. The extension of the nuclear capacity has also been considered responsible for the missing political will to grant more support for renewables due to the fact that the additional nuclear capacity would not be justifiable if a noteworthy amount of renewables was deployed in the country. Furthermore, experts have raised concerns that due to the political line which is clearly pro nuclear energy, the support for the PV sector could be cut anytime following the example of the wind energy which has been practically banned in mid-2016 through one governmental decision.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE20
Category: Political and economic framework
Sub-Category: Reliability of general RES strategy
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The National Renewable Energy Action Plan from 2010 foresaw introduction of the Renewable Energy Act. However, this has not been realised so far. The Renewable Energy Act was expected to encompass all RES-related issues such as the feed-in and premium tariff system regulating provisions and probably the licensing procedure in one legal act. Instead of having introduced that one act, the RES-E framework was changed through simply amending the Electricity Act (amendments in effect as of January 2017). In addition, some specifications on the remuneration scheme were defined within Ministerial/Authority Decrees. In this context, the introduction of Renewable Energy Act is not expected in the near future.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: HUE21
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Wind power plants can only be realised on the basis of a tender, which is necessary for the authorisation procedure and the construction of wind power plants. So far, only one tender has been launched allocating 330MW installed capacity in 2009. A second tender for 410MW had been cancelled in 2010. For now, there is no information about future tenders for wind power plants and uncertainty in the wind power sector is very high. No additional capacity for wind power is expected in the upcoming years due to the fact that high administrative burdens have been imposed with regard to the construction of wind power plants in mid-2016. Furthermore, connection of additional capacity to the public grid is impeded by a Government Decree, which allows no new capacities in 2016-2018 .

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE22
Category: Political and economic framework
Sub-Category: Existence of RES support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

If operators of RES-plants exceeding 500 kW estimate their electricity production erroneously by more than 30-50% (depending on the technology), they are obliged to pay financial penalties for every incorrectly given kWh. This strict scheduling system is perceived as a high administrative burden and is one of the main reasons why the investors decide against the plant construction.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE23
Category: Administrative processes
Sub-Category: Cost of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Inter alia due to the non-market-based electricity pricing (which is the result of the governmental policy of low expenses), incentives for energy efficiency and the deployment of renewable energy sources are missing, especially in the residential sector.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE24
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The evolvement of domestic RES market is remarkably hindered by the shortage of RES-experts and this shortage is permanently increasing. In general, workforce is outstandingly expensive for the companies and the salaries are not attractive to employees. Consequently, skilled workers are leaving Hungary to work abroad (Germany, Austria, etc.).

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE25
Category: Other
Sub-Category: Training
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In Hungary, a remarkable centralization of different political spheres has taken place since 2010. However, for the deployment of RES, the principle of decentralization is more suitable. The majority of RES installations require local solutions due to the fact that, opposed to huge facilities, their capacity per unit is low. For example, the grid infrastructure has been developed for large electricity producers and transmission is regulated on a national level. If e.g. municipalities had more authority, they could elaborate an own energy strategy (incl. infrastructural issues), integrating civil RES participation projects as well into their local energy mix.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE26
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

As of September 2016, special restrictions for wind power plants have been introduced, e.g.: - The wind power plant’s capacity may not exceed 2 MW. - The distance between the rotor blades and the ground may not be less than 50 m and are not allowed to be longer than 50 m. According to a study called “Where the wind blows” (“Honnan fúj?”) from the Regional Centre for Energy Policy Research (REKK) which examined a sample of 208 currently produced plant types, this has been considered one of the most severe barriers since only 30% of the examined plants fulfil this requirement. If it would be 40 m, more than 50% of the examined plants (which are currently produced) would fulfil the criteria. According to the study, the consequence of the regulation is that leading manufacturers like GE, Enercon, Goldwind and Gamesa will not be able to enter the Hungarian market. - The height of the plant may not exceed 100m, shall not interfere with air traffic, radio communication or communication for military and defence purposes. However, the most important and significant barrier to the construction of new wind power plants is the modification of the regulation on national site planning and building requirements. This Government Decree determines that wind turbines (or wind parks) are not allowed to be constructed in the areas for building purposes and within a range of 12 kilometres from their borders. In fact, there are no areas for the construction of wind power plants in Hungary which would meet this criteria. With regard to the new regulations, the Hungarian government explains that the installation of additional wind capacity is not foreseen because the net capacity is insufficient and ‘negative experience’ with controlling wind energy in other countries has a deterring effect.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE27
Category: Administrative processes
Sub-Category: Integration of RES in spatial and environmental planning
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Aside from the FiT and the green premium, depending on the RES-technology project developers might be eligible for the investment grants within tendering procedures, which are released in undetermined time intervals. However, it has been observed that applications are often submitted by the same market players, given the fact that great experience with the administrative procedures is necessary to win a tender. Consequently, it is barely possible for new market players to participate in tenders as the procedure itself is considered sumptuous and opaque. According to the Hungarian PV sector, it makes no sense to participate in tenders, because ‘the winner is known in advance’. The latter statement is supported by the fact that there were several inconsistencies concerning tenders which were revealed and became public recently. Furthermore, the projects which are realised through tenders are not considered cost efficient and competitive on the free market. PV projects realised through tendered financial means are 20-100% more expensive than projects realised through other investments in Hungary. Those projects operate on approx. 30-40% higher costs than not tendered projects. Foreign investors are well aware of the situation and do not even try to access investment through tendering procedures. All in all, the tendering for EU-funds is considered complex and is linked to uncertainties and administrative burden.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE28
Category: Political and economic framework
Sub-Category: Access to finance
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In almost all cases, only public institutions are eligible for EU-funds for RES projects. This has created a distorted market situation where the project costs are not in line with the market prices. In general, the state is the main beneficiary of the EU-funds which is not considered reasonable with regard to the opportunities for RES-E in the private sector. As a consequence, potential capacities remain unused.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE29
Category: Political and economic framework
Sub-Category: Access to finance
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

An ‘environmental’ tax has been imposed on solar panels in 2015. The tax rate amounts up to 114 HUF/kg (approx. 0.37 €/kg) leading to a substantial rise in costs: for PV plants with high capacities the tax means a significant additional financial burden which is also confirmed by investors in the PV sector. Furthermore, the amount is not considered reasonable with regard to the fact that the batteries and accumulators are charged with 57 HUF/kg (approx. 0.18 €/kg). In addition, the environmental tax has to be declared to the tax authority which means an additional administrative burden for plant operators. According to the Hungarian Solar Association, the political constraints including the taxation policy have led to the fact that Hungary has the highest payback time for PV installations/plants in the European Union.

Component Authority:  Földművelésügyi Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE30
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In Hungary, the high value added tax (VAT) of 27%, which is the highest in the EU, is considered a high impediment for investment projects. PV installations are also negatively affected. In consequence, components are predominantly supplied by foreign companies whom national producers cannot compete with due to the Hungarian taxation policy.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE31
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In 2015, fire protection regulations have been introduced which also negatively affect PV installations. In consequence, system installers are obliged to mount a fire protection switch which corresponds to 10-15% of the overall project costs.

Component Authority:  Belügyminisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE32
Category: Administrative processes
Sub-Category: Cost of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The electricity grid infrastructure in Hungary is not designed to integrate a significant amount of RES-E. According to the experts, the infrastructure is extremely outdated. Due to the fact that the energy prices for households are determined by the energy authority (Hungarian Energy and Utility Regulatory Authority (HEA) – Magyar Energetikai és Közmű-Szabályozási Hivatal (MEKH) and are kept artificially low, the energy suppliers had to make further savings which were made at the expense of grid development. Furthermore, the energy suppliers rather invested into grid development in neighbouring countries like Slovakia, where the rate of return was considered more attractive for the investors.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE33
Category: Grid regulation and infrastructure
Sub-Category: Lack of infrastructure and infrastructure development
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Under the net metering scheme, the DSOs in Hungary are obliged to integrate the electricity from RES-E installations up to 50 kW and to store it for free. With regard to the low electricity prices for households, the net-metering is considered an additional burden for DSOs. There are no incentives for them to integrate RES-installations and RES-E has no good standing among DSOs.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: HUE34
Category: Political and economic framework
Sub-Category: Remuneration level for RES
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The administrative costs for RES plants with a capacity of 500 kW or more are increasing considerably - daily production quantities of electricity for the previous day have to be reported to the energy authority, which is time-consuming and costly, especially for smaller and medium-sized companies. If the production is evaluated erroneously by 30-50% (depending on the technology), the plant operator has to pay penalties of 5-7 HUF/kWh (approx. 1,6-2,3 €ct/kWh) for the amount erroneously estimated.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE35
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

According to the amended building licensing regulations, the RES project developer has to hand in an evidence indicating that the selected site cannot be used as arable land/it has not been used as arable land for at least three years. This is a retroactive measure applied also to already planned and almost realised projects. As a result, these projects have to be stopped if they do not fulfil these criteria.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE36
Category: Administrative processes
Sub-Category: Integration of RES in spatial and environmental planning
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The legal framework provides no incentives for civic participation in renewable energy projects. Currently, civic participants are unable to use the generated electricity themselves but have to sell it instead, which is considered a taxable income. Due to the fact that the electricity has to be sold, purchasing a jointly used system is not attractive. Therefore, there are barely any civic participation projects in the field of renewables in Hungary.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE37
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In January 2017, the Hungarian Energy and Utility Regulatory Authority released a decree on (the possibility of) introducing system usage fees for household installations >4 kW. Currently, the fee is set to 0€, but it is expected that it will be raised in the near future. Currently, the conditions for small installations up to 50 kW are considered quite favourable due to the net-metering system and the absence of connection and usage fees in this segment. However, the new system usage fee would mean an additional burden for installers since the payback time for RES-installations in Hungary is already considered one of the highest in the EU: A value added tax (VAT) of 27%, environmental taxation on PV-panels and missing investment grants are the main factors for the high payback time.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: HUE38
Category: Grid regulation and infrastructure
Sub-Category: Cost of RES grid access
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Financial support for RES in the H&C sector is only allocated in terms of grants, for example by the Environment and Energy Operative Programme (KEHOP), Rural Development Programme (RDP) and the Economic Development and Investment Operational Programme (EDIOP), but there might be funds allocated from other programmes as well. These Programmes are allocating financial means mainly provided by the the European Cohesion Funds. However, available grants are not sufficient to exploit the high potential of renewable energy in the heating sector. This problem is indicated, e.g. when subsidy programmes are closed due to exhausted funds only few days after being launched. However, the budget of available funds under the financing period 2014-2020 (for example) of the KEHOP subsidy programmes increased compared to the previous financing period.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: HUHC01
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The frequency of calls for projects, especially under the Green Investment Scheme (GIS), is unreliable and little predictable as the GIS-related programmes are financed by revenues from Hungarian EUA units. Furthermore, the time period regarding the programmes’ availability is also unreliable. Calls for programmes may end before the announced deadline due to exhausted funds. The last project within this scheme was realised by the end of 2014. The Green Financing Programme is also financed by revenues from ETS quota sales and from the state budget, so that availability of funds for this programme is expected to be more reliable. However, experience has shown that the system is not transparent and that some amounts are only spent for e-mobility but not for the RES-H&C. In the latter case, e.g. under the sub-programme called “Warmth of Homes”, which is addressing private households, funds are depleted within hours. However, it is difficult to plan thermic refurbishments due to the fact that there is no tender schedule.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: HUHC02
Category: Political and economic framework
Sub-Category: Reliability of RES support scheme
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Market development and actual demand for RES-H&C installations is strongly driven by availability or lack of public funding. Taking solar installations as an example, subsidy programmes and the foreseen time frame under the programme for realising projects have caused huge demand for the solar installations, so that Hungarian producers and installers could not live up to this drastically increased demand. These unpredictable framework conditions undermine a steady market development for RES-H in Hungary and hamper a solid capacity planning of producers and installers.

Component Authority:  Magyarország Kormánya
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC03
Category: Political and economic framework
Sub-Category: Existence of RES support scheme
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Geothermal projects are facing uncertainties with regard to the temperatures and capacities they find on the site. Even the required drilling depth can only be finally determined when the well is built. Aside from technical risk modelling techniques, financial risk management solutions are necessary to promote the development of geothermal generation. These revenue risks hamper exploring the vast geothermal potential across the country. Even though various subsidy programmes address also geothermal projects, the revenue risks for covering the own financial contribution are still very high. Due to the many unknown factors regarding geothermal drilling, project costs may sharply increase in the course of realising the project, e.g. for determining the adequate drilling depth. In other cases, the project might be cancelled shortly after starting the drilling. Thus, it is very difficult to determine an adequate support level within the various subsidy programmes.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC04
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Pricing provisions for district heating do not allow for reflecting the higher financial risks of Geothermal. This undermines Geothermal’s profitability. As regards geothermal district heating that supplies heat energy to households, only project costs of realised geothermal projects can be included in the final heat prices. The expenses for cancelled, unrealised geothermal projects cannot be passed on the final consumers. However, in case of final consumers other than households, e.g. public authorities or enterprises, the supplier is free to agree on a price bilaterally. In order to address this problem, a working group has been initiated aiming at alternative solutions.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: HUHC05
Category: Political and economic framework
Sub-Category: Access to finance
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Within district heating prices, the share dedicated to infrastructure development and renewal is very low. The share of investments and capital costs for infrastructure development, that can be passed on to final consumers through district heating prices is three to four times lower in Hungary than in Western European countries. Thus, district heat companies face difficulties to bring up the own financial contribution for infrastructure development. For this reason, banks started to ease financing of projects on developing the district heating network. Moreover, a district heating development plan has been scheduled since 2011 in order to structure the financing of the district heating development. However, it has not been implemented yet.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: HUHC06
Category: Grid regulation and infrastructure
Sub-Category: Lack of infrastructure and infrastructure development
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

A reliable overview of all necessary administrative steps to be taken and all documents and applications to be handed for RES&H projects in is missing in Hungary. Furthermore, a very high number of authorities is involved in the administrative process. This is also due to overlap of responsibilities of different authorities and insufficient delimitation of responsibilities. As it is, the transparency concerning Hungary’s management of environmental issues is more and more questionable: Currently, there is no Ministry for Environment in Hungary, the position of the ombudsman for green issues has been abolished and other green authorities have been withdrawn. Instead of fostering the institutionalization of managing environmental issues in a transparent manner, the opposite is happening.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC07
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Even though not all authorities have to be attended in person, the processing times take long and may easily be delayed for diverse reasons (e.g. illness of the responsible person). It is envisaged to reorganise the whole administrative procedure toward a one-stop licensing system, but this requires immense internal reorganisation in Hungarian authorities. Currently, the efficiency potentials to be realised by this measure are unknown.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: HUHC08
Category: Administrative processes
Sub-Category: Duration of administrative procedure
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Public perception of district heating is quite negative and households tend to refuse district heating because it is considered being too expensive. This constitutes a barrier to the deployment of biomass and geothermal heating. In addition, individual heating systems increase the value of a real estate compared to utilisation of district heating making district heating less attractive for households. The Awareness Raising Action Plan finalised in 2014 defines various awareness raising measures in order to achieve Hungary’s renewable energy, energy efficiency and GHG targets and might ease this problem. These awareness raising measures are partly conducted by the Hungarian Association for district heating suppliers (Magyar Távhőszolgáltatók Szakmai Szövetsége - MATÁSZSZ).

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: HUHC09
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

With regard to statistics, the level of information and information availability about RES-H&C technologies and their potential is deficient. Local administrations, for example, are very often not even aware how much they spend on heating for their real estates and what type of heating system is installed in the buildings not to mention the potential of RES-H&C installations. This hampers the implementation of RES-H&C projects.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: HUHC10
Category: Other
Sub-Category: Statistics
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The lack of training programmes for RES-H&C installers and craftsmen refers to vocational and academic training. Furthermore, specialists often emigrate. In order to address this problem the IEE programme “BUILD UP Skills TRAINBUD” launched in 2014 foresees trainings in the field of energy efficiency and renewable energy technologies.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: HUHC11
Category: Other
Sub-Category: Training
Affected Technologies:
Geothermal energy
RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Hungary has huge thermal water resources (thermal leachate) with 30-50C which could be used by means of heat pump systems in the heating sector. Currently, however, there are no financial incentives to make use of this possibility.

Component Authority:  Földművelésügyi Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC12
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The value added tax (VAT) for renewable energy installations is high and amounts to 27%. Taking into consideration that most subsidy programmes grant approx. 30-35% of eligible costs, this is just sufficient to cover the tax expenses. Consequently, especially when no subsidy can be obtained, RES-H&C installations are set up very often without billing. In this way, renewable energy installations are usually realised even without financial support.

Component Authority:  Nemzeti Gazdasági Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC13
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In the Pannonian Basin, due the porous geographic structure, reinjection proves to be technologically extremely difficult. This leads to increased costs and energy demand for geothermal heat generation and decreases the profitability of these projects. Reinjection obligations threatened to cause existing geothermal producers to switch to natural gas utilisation or to shut down the power plants. As a consequence, in 2012, the Parliament postponed reinjection obligations until 2015 and extended the postponement until 2025 in March 2013, exempting existing geothermal plants from reinjection obligations. Though, on the long run, the question remains how sustainable the use of geothermal sources is without reinjection. So far, scientific positions and evidence is inconsistent regarding the effects of lacking reinjection.

Component Authority:  Magyarország Kormánya
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: HUHC14
Category: Other
Sub-Category: Operational issues
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The ongoing reduction of final consumer prices for energy including natural gas, electricity and district heating undermines financial incentives to switch to RES-H&C installations. Taking into consideration the diminished prices for natural gas, the amortisation period for renewable energy installations increased, thus becoming less profitable and economically less justifiable. In general, lower costs for household expenses is part of the government’s policy. However, the artificially low prices for e.g. gas have to be compensated somehow. In consequence, additional costs are not directly visible to tax payers and are barely traceable. This creates a bias in the perception of energy prices which is not obvious to the broad population. Therefore, the switch to RES is not perceived as being cost-efficient.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC15
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Biomass (basically wood incineration) has the highest share within the Hungarian RES-mix and contributes the most in order to fulfil the domestic RES-target. In 2014, from the total renewable energy, 66% were generated in the heating sector, 17% in the electricity and 17% in the transport sector. Expressed in numbers, the total RES production in 2014 was 64 PJ, from what 43 PJ were generated through wood incineration, 8.2 PJ through biofuels, 5.2 PJ through Geothermal, 1.8 PJ with biogas, 2.5 PJ through wind energy, hydro 0.8 PJ, 0.5 PJ with heat pumps and 0.5 PJ with solar energy. However, wood is not incinerated out of environmental but economic considerations and cannot be assessed expedient in the framework of the normative goals of the RES-directive. It is not appropriate to establish wood incineration as the main renewable energy source. Although Hungary is expected to reach its obligatory 2020 RES-target of 13% in final energy consumption, this will happen through an unbalanced deployment of different renewables energy sources. Due to the extensive wood incineration, there is a lack of financial incentives for other technologies.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC16
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Hungary has a very well developed natural gas grid infrastructure, covering 90% of the Hungarian households. Although biomethane could make full use of the existing infrastructure, due to the missing financial incentives for this technology potential capacities remain untapped. In consequence, landfill gas for example is only partly electrified on spot but could also be easily upgraded and injected into the natural gas grid with the respective support mechanisms.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC17
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Most of the heat generated in biogas plants remains unused due to a lack of financial incentives supporting the efficient use of heat energy. For support schemes other than the FiT, only new projects are eligible at the moment.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC18
Category: Political and economic framework
Sub-Category: Existence of RES support scheme
Affected Technologies:
Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In some cases, the costs/ complexity of the grid connection procedure depend on the relationship between the DSO and the plant operator.

Component Authority:  DSOs
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: HUHC19
Category: Grid regulation and infrastructure
Sub-Category: Predictability / transparency of connection procedure
Affected Technologies:
Biofuels
RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The political strategy regarding biofuels is quite contradictory. On the one hand, investments into biofuel generation and biomass cultivation are politically desired and authorities are eager to enable these investments. Even foreign investors appreciate the good geopolitical conditions, the high agricultural potential and the very good availability of raw materials for biofuel production. On the other hand, a consistent strategy for increasing domestic demand for biofuels produced in Hungary is missing. Consequently, approx. 90% of Hungary’s bioethanol production is exported. At the same time, Hungary imports fossil fuels to meet the country’s energy demand. From an environmental perspective, the local utilisation of domestically produced biofuels would be much more preferable.

Component Authority:  Nemzeti Fejlesztési Minisztérium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Transport
Code: HUT01
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Biofuels
RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.