Skip to main content

Electricity

Barrier index per category and technology

Heating and Cooling

Barrier index per category and technology

Transport

Barrier index per category and technology

Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The German Federal Building Code (Baugesetzbuch-BauGB) was amended in 2014 to provide the possibility to federal states in Germany to adopt specific minimum distance rules to residential areas for Onshore installations. The legal time frame for adopting such rules was 31 December 2015. Only the federal state of Bavaria made use of this provision and adopted the so called 10H rule which prescribes that the minimum distance for Onshore energy projects to residential areas must be larger than 10 times the hub height. This has significantly constrained the development of Onshore projects in Bavaria. Other federal states have decided not to adopt the uniform distance rules but the distance rules are specified by regional and local authorities on a project base.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Policy Recommendation: Abolition of the 2014 legislative framework for existing RES-E plants

The RES-E projects had been planned and developed in the past according to other rules that were changed in the middle of the process, imposing sever financial losses and seriously jeopardizing the legal security in the RES sector. Thus, project developers are claiming to keep the initial legal rules not only to continue receiving the profits they had received before July 2013, but also for the re-establishment of the legal security.

Sector(s): Electricity
Code: DEE01
Category: Administrative processes
Sub-Category: Integration of RES in spatial and environmental planning
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

As of 2017, new renewable energy projects do not receive the guaranteed feed-in tariff but must be successful at the public tender to receive the financial support (only small solar and Onshore installation of up to 750 KW and biomass of up to 150 KW are exempted). The up-front administrative costs of preparing for and participating in tenders are higher than in the case of the support scheme based on the government-set prices. The administrative expenses are not refundable if the project is not successful.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE02
Category: Administrative processes
Sub-Category: Cost of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The expansion of transmission grids is progressing slowly due to the complex and interlinked responsibilities between the central government and federal states. The privately-owned transmission system operators do not have a strong incentive to expand the grid as needed to integrate the increasing share of renewable energy sources. The opposition of local communities also plays an important role. Finally, the decision to install underground cables for power transmission from North to South of Germany has caused further delays in the development of the grid due to the higher technical challenges and longer time needed for placing underground cables compared to standard overhead powerlines.

Component Authority:  TSOs
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE04
Category: Grid regulation and infrastructure
Sub-Category: Transparent and foreseeable grid development
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The wind energy industry and the military have initiated a dialogue on the issue and progress has been made. But another aspect of the problem is the proximity of wind power plants to civil radar stations, for example those of meteorological services or civil aviation. Cooperation with the German air traffic control and the German weather service proves to be more difficult and constitutes a more serious barrier.

Component Authority:  Bundesministerium der Verteidigung
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE05
Category: Administrative processes
Sub-Category: Integration of RES in spatial and environmental planning
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The designation of land areas where wind energy plants can be built as part of the land-use plans is responsibility of regional authorities (federal states and local governments). The process of adopting the regional land-use plans, including wind priority areas, often takes too long; in some cases several years. This is mainly due to the requirement of public participation which makes the adoption process cumbersome. In turn, the implementation of wind energy projects is slowed down.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE06
Category: Administrative processes
Sub-Category: Integration of RES in spatial and environmental planning
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Renewable energy plants which benefit from the support scheme and which are obliged to directly market the produced electricity are required to install remote control systems. Such systems should enable electricity traders to control and if necessary curtail the electricity production from renewable energy plants. This obligation was introduced under the Renewable Energy Act from 2014 and maintained in the Renewable Energy Act from 2017. It applies to facilities of more than 100 kW of the installed capacity or other facilities which directly market the produced electricity. This provision poses a barrier for smaller installations due to the high costs of installing the remote control systems. Further problem is that this provision applies also to the existing renewable energy installations, which retroactively decreases their economic feasibility. Finally, the firm technological standards for the remote control systems are not present.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: DEE09
Category: Grid regulation and infrastructure
Sub-Category: Treatment of RES dispatch (curtailment)
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Existing renewable energy installations are subject to paying 20% of renewable energy surcharge (EEG-Umlage) for self-consumed electricity, if substantial modernization of the installation is undertaken. This places additional costs and decreases revenues for the existing installations.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE10
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Due to the past dynamic development of the biogas sector and also due to some instances of damages in biogas plants (accidents, loss of control, etc.), the subject of safety is very high on the agenda. The complex and often not clearly defined safety regulations pose a barrier for some investors in biogas plants. As a result, some biogas projects failed to be realized.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE11
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Under the new Renewable Energy Act, the government has the possibility to introduce further regulations to promote the use of renewable energy sources in rented properties. Such regulations is prepared but has not yet been adopted. It is seen as necessary in order to place under same conditions the self-produced and self-consumed electricity by lenders and by tenants. Currently, tenants pay the full renewable energy surcharge on every kWh of the consumed renewable electricity whereas property-owners do not pay any surcharges on the consumed electricity

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE12
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Solar PV plants of the installed capacity of more than 10 MW are not supported under the Renewable Energy Act due to the impact on land utilization.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: DEE13
Category: Political and economic framework
Sub-Category: Existence of RES support scheme
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Ground-mounted solar PV systems on arable land are generally excluded from receiving remuneration under the Renewable Energy Act. Only up to 10 solar PV projects annually can be built on arable land in specifically defined disadvantaged regions. This not only reduces the available area for building solar PV installations, but it is also problematic given than in other countries it is allowed to build solar PV installations on arable land (e.g. Denmark). This leads to the distortion of competition in cross-border tenders for solar PV.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE14
Category: Administrative processes
Sub-Category: Integration of RES in spatial and environmental planning
Affected Technologies:
Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The floor price for the auction round for new biomass plants in 2017 is set at 14,88 c/Kwh and is too low for most of the installations to be economically feasible. The feed-in tariff level for new biomass plant of less than 100 Kw of the installed power is set at 13,2 c/KWh and is also considered to be too low. This does not apply to plants fueled by bio waste and liquid manure, which receive higher feed-in tariffs.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: DEE15
Category: Political and economic framework
Sub-Category: Remuneration level for RES
Affected Technologies:
Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Large geothermal projects are characterised by high capital requirements. The upfront financing is very difficult both for private investors and municipalities. Banks will only give low interest loans if the risks for the borehole are borne by the investor or by somebody else (the costs can amount to several million euros). Some insurance companies offer financial products to cover to some extent the financial risk in the exploration phase. Additionally, the Federal Market Incentive Programme (MAP) provides grants for covering a part of the investment costs for drilling boreholes. Up to four boreholes by project can be financially supported. This does not include exploration activities but it provides overall more financial feasibility for investors.

Component Authority:  Banks
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE16
Category: Political and economic framework
Sub-Category: Access to finance
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Electricity storage capacities are considered to be both energy producers and end-users under the current legislation. This implies that they are subject to costs (levies and taxes) related to grid use and energy consumption. This damages the financial viability of using electricity storage capacities (e.g. batteries). In turn, the technologies which rely on electricity storage such as power to gas and which should enable better coupling of renewable energy use across sectors are insufficiently deployed.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE18
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The pumps for operating a geothermal power plant often encounter technical problems due to the process of scaling. This causes problems in the operation of pumps which has serious implication on the acceptance and financial feasibility of geothermal projects.

Component Authority:  Manufacturers
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE19
Category: Other
Sub-Category: Operational issues
Affected Technologies:
Wind power
RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The administrative requirements for Offshore energy projects are high and stricter than in many other countries. This relates to the large number of documents (e.g. studies) that must be collected and the level of technical details that must be addressed before commissioning the Offshore farm.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE20
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The Renewable Energy Act (EEG) which entered into force in 2017, has introduced annual expansion targets for renewable energy projects in solar PV, biomass, Offshore and Onshore in combination with the public tenders. These expansion targets should provide more stability in planning the deployment of renewable energy sources and ensure better coordination with grid development. However, the targets are regarded as too low and not adequate to fully exploit the physical and industrial potential in the renewable energy sector. For Offshore energy, the problem is particularly prominent given the tight capacity targets especially in the period until 2025 and only few tender rounds.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE21
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

For geothermal projects, permits have to be obtained from the mining and water authorities. The time necessary for obtaining these permits can differ greatly, making it difficult for operators to have any planning certainty. In addition, drilling rights are handled differently in different states, making it difficult for them to exchange experiences about projects. It may therefore be impossible to issue best practice recommendations, which could reduce the planning time. Furthermore, the long time for processing applications hampers a rapid project implementation..

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE22
Category: Administrative processes
Sub-Category: Duration of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

For RES-E projects in general, public acceptance is rather high, primarily because of public participation. However, there are still projects which encounter problems. This relates primarily to Onshore, Offshore, biogas and Geothermal projects. For example, geothermal projects have to contend with citizens' initiatives that oppose this form of energy for various reasons. These include risks (such as seismicity) and the economic inefficiency of projects. Public acceptance for biogas and some Onshore energy projects is also declining due to the negative impact on local communities (e.g. noise, smell, landscape). Some planned Offshore projects also face local resistance due to, for instance, the possible negative impact on landscape and tourism.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE23
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Wind power
RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The current regulation does not foresee the differentiation in premium tariffs for Offshore projects installed in different water depths. This may make offshore projects which are located further from the shore less financially attractive.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE24
Category: Political and economic framework
Sub-Category: Remuneration level for RES
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The anti-dumping measures against solar panel manufacturers from China adopted at the EU level impose additional taxes on imported solar PV panels from China. This leads to the higher price of installations of solar PV in Germany

Component Authority:  European Commission
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE25
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

As of 2017, the tendering system is introduced as an obligation for new projects in solar PV, Onshore, Offshore, biomass and CHP above a certain size of the installed power. Only most cost-effective projects which are successful in the public tender can obtain the financial incentives in the form of a market premium. The new support scheme will bring considerable uncertainty for investors, particularly small-size project developers and citizens initiatives as they are not able to effectively manage the risks and high administrative demands associated with the tendering system. The tendering system has largely been imposed by the European Union´s Guideline for State Aid for Environmental Protection and Energy.

Component Authority:  European Commission
Sector(s): Electricity
Code: DEE26
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The new regulation imposes rather strict annual volume limits for onshore and Offshore energy in North Germany due to the bottlenecks and overburdened power grid. Additionally, some areas comprised by volume caps for Onshore are overly broadly defined and tend to include areas where bottlenecks do not appear.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE27
Category: Grid regulation and infrastructure
Sub-Category: Transparent and foreseeable grid development
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The existing electricity market does not facilitate a larger integration of renewable energy sources. Renewable electricity is already the dominant generation technology on the short-term markets, but these markets are not yet consistently designed for them. Renewable electricity is increasingly curtailed because the grid does not have sufficient capacity and the production facilities based on nuclear and coal energy continue to run and overload the grid. This is due to the fact that the short-term market does not give adequate price signals for the development of flexible reserve capacity, smart grids and electricity storage capacities, which are all necessary for the larger integration of renewable energy sources.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: DEE29
Category: Market structure
Sub-Category: Existence of functioning and non-discriminatory short term markets for RES
Affected Technologies:
Biomass
RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Since 2012, no financial support under the Renewable Energy Act is provided for the electricity from bio-liquids.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: DEE30
Category: Political and economic framework
Sub-Category: Existence of RES support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Under the current regulatory framework, for electricity produced in renewable energy sources and consumed on site, 40% of Renewable Energy Surcharge (EEG-Umlage) must be paid. This rule is effective from 2017 and applies only to newly installed renewable energy facilities. Renewable energy installations of less than 10 kW as well as off-grid installations are exempted from the EEG-Umlage.

Component Authority:  European Commission
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE31
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

For geothermal projects, permits have to be obtained from the mining and water authorities. Permitting procedure tends to be overly complex and highly demanding in terms of safety and environmental standards. In addition, drilling rights are handled differently in different federal state units. Finally, the regulation on the location selection for the disposal of nuclear waste which was amended in 2017, makes virtually impossible for implementing deep geothermal projects in the regions in Central and Northern Germany which are identified as suitable for nuclear waste disposal.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: DEE33
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The new Renewable Energy Act from 2017 foresees that premium tariffs for new renewable energy installations will be reduced to zero during the period when electricity market prices on the spot market are negative for more than six consecutive hours. This does not apply to wind energy installations of less than 3 MW and all other technologies with the installed capacity of less than 500 kW. It is still unclear how severe the implications of this regulation will be for the profitability of new renewable energy projects . This provision has largely been imposed by the European Union´s Guideline for State Aid for Environmental Protection and Energy.

Component Authority:  European Commission
Sector(s): Electricity
Code: DEE36
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The financial support for renewable energy projects is not adjusted for inflation. This poses a minor revenue risk for renewable energy investors.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: DEE39
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The Renewable Energies Heat Act (EEWärmeG) prescribes the use of renewable energy heating only for new buildings but not for the modernization of the existing building stock. This hinders larger deployment of renewable energy technologies in the existing buildings. The Law does allow the possibility for federal states to introduce additional energy efficiency requirements for the existing buildings. The federal state Baden Württenberg, for instance, has adopted such measures.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: DEHC01
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The Renewable Energy Act (EEG) which entered into force in 2017, has introduced annual expansion targets for renewable energy projects in combination with the public tenders. These expansion targets should provide more stability in planning the deployment of renewable energy sources and ensure better coordination with grid development. However, the annual targets for biomass (150 MW for 2017-2019 and 200 MW for 2020-2022) are seen as too low and not adequate to fully exploit the natural and industrial potential in the biomass energy sector. This negatively affects the realization of CHP biomass plants which rely on the support scheme under the Renewable Energy Act for selling the produced electricity.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: DEHC02
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Existing renewable energy installations are subject to paying 20% of renewable energy surcharge (EEG-Umlage) for self-consumed electricity, if substantial modernization of the installation is undertaken. This provision affects CHP plants and places additional costs and decreases revenues for the existing installations.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: DEHC03
Category: Political and economic framework
Sub-Category: Revenue risk under given support scheme
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Fossil fuel sources used for heating are not sufficiently taxed considering the negative environmental externalities which they cause. Due to this fact, renewable energy heating technologies are disadvantaged.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: DEHC04
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The calculation method of the turnover tax for the heat produced in CHP plants for self-consumption is not properly defined. The financial authorities take as a starting point the lack of the CHP heating market and take the average heating prices in the district heating network as the basis for calculating the turnover tax. Some court decisions, however, have challenged this position. The decisions tend to be made on the case to case basis.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: DEHC13
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The pumps for operating a geothermal power plant often encounter technical problems due to the process of scaling. This causes problems in the operation of pumps which has serious implication on the acceptance and financial feasibility of geothermal projects.

Component Authority:  Manufacturers
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: DEHC28
Category: Other
Sub-Category: Operational issues
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

For geothermal projects, permits are required from the water and mining authorities. The time necessary for obtaining these permits can differ greatly, making it difficult for operators to have any planning certainty. In addition, water and mining rights are handled differently in different states, making it difficult for project developers to exchange experiences about projects. The long time to process applications hampers a fast project implementation.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: DEHC29
Category: Administrative processes
Sub-Category: Duration of administrative procedure
Affected Technologies:
Geothermal energy
RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Electricity used for heat pumps is subject to a plethora of duties and taxes as much as for any other electricity consumer. This includes electricity tax, renewable energy surcharge, value-added tax and grid-use charges. As a result, the competitiveness of heat pumps in comparison to fossil fuels for heating is damaged.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: DEHC30
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

For geothermal projects, permits have to be obtained from the mining and water authorities. The permitting procedure tends to be overly complex and highly demanding in terms of safety and environmental standards. In addition, drilling rights are handled differently in different federal state units. Finally, the regulation on the location selection for the disposal of nuclear waste which was amended in 2017, makes virtually impossible for implementing deep geothermal projects in the regions in Central and Northern Germany which are identified as suitable for nuclear waste disposal.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: DEHC31
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Geothermal energy
RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The constant public focus and the negative outlook on electricity prices leads to consumers having a negative perception of electricity as heating fuel.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: DEHC32
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There are three legal documents, which currently regulate the issue of energy efficiency of buildings: Energy Saving Act (Energieeinsparungsgesetz - EnEG), Renewable Energies Heat Act (Erneuerbare-Energien-Wärmegesetzes - EEWärmeG) and Energy Saving Ordinance (Energieeinsparverordnung- EnEV). Some provisions in these regulations which concern energy efficiency in the building sector, including the use of renewable energy technologies such as heat pumps and solar thermal, are not fully aligned, which increases complexity and hinders effective policy implementation. For instance, the calculation methods for energy efficiency improvements vary in different regulations. The barrier is acknowledged by the competent ministry and the merger of these regulations is seriously considered.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: DEHC34
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Geothermal energy
RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Consumers are not sufficiently aware of the existence and benefits of renewable heating. This is partly due to poorly implemented regulations on energy passports of buildings in federal states which have not sufficiently contributed to increasing awareness about the legal standards and benefits concerning the use of renewable energy sources for heating.

Component Authority:  Local authorities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Heating and Cooling
Code: DEHC36
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Electricity
RES-T electricity
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The installation of charging stations for electric cars on the rented property faces obstacles. The major issue is who bears the costs of installing charging points for electric vehicles in, for instance, garages of residential buildings. The regulation which should address this problem is in preparation.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Transport
Code: DET01
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Biofuels
RES-T gaseous biofuels (biomethane)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T gaseous biofuels (bio-CNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bio-LNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The current regulatory framework in the transport sector focuses on the fulfilment of the Fuel Quality Directive (6% GHG reductions by 2020) and less on the RES-T target (10% renewables by 2020). The focus is on the latter based on the assumption that this will also lead to implementing the former. There is uncertainty about that. There is also general uncertainty concerning the overall demand for biofuels through 2020: how much biofuels will actually be needed to meet the target of 6% GHG reduction? Under the current framework, biofuels are seen as victims of their own success: the more GHG efficient biofuels are, the less there will be need for biofuels because the GHG reduction quota will be met more quickly. Finally, the GHG reduction targets lack annual stability; for the period 2017-2019 the reduction target is set at 4% and for 2020 at 6%. Such considerable increase in one year is not realistic and more mid-term targets are needed.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Transport
Code: DET41
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Biofuels
RES-T gaseous biofuels (biomethane)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T gaseous biofuels (bio-CNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bio-LNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T other biofuels
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The EU biofuel market remains fragmented and insufficiently regulated. The support schemes for biofuels vary significantly across EU member states and EU rules and standards on biofuels are often poorly enforced. This prevents the trading in biofuels across the EU and thus hinders the investments and development in the biofuel sector in Germany and other member states.

Component Authority:  European Commission
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Transport
Code: DET42
Category: Market structure
Sub-Category: Fair and independent regulation of the RES sector
Affected Technologies:
Biofuels
RES-T gaseous biofuels (biomethane)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T gaseous biofuels (bio-CNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bio-LNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T other biofuels
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Since 2015, biofuels are not subject to any tax reliefs in Germany. This makes biofuels less competitive compared to traditional fossil fuels.

Component Authority:  Bundesfinanzministerium
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Transport
Code: DET43
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Biofuels
RES-T gaseous biofuels (biomethane)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T gaseous biofuels (bio-CNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bio-LNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T other biofuels
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There is considerable uncertainty among the biofuel industry about the post-2020 period. Particularly in light of the debates at the EU level and the proposal of the EU Commission to reduce the quota for first-generation biofuels down to 3,7% by 2030 due to the indirect impact on land use change (ILUC). Production of first generation biofuels is important source of revenues for farmers in Germany. Some by-products of biofuel production (e.g. soy) are used as food for animals and would not be economically feasible without the revenues from selling biofuels.

Component Authority:  European Commission
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Transport
Code: DET44
Category: Political and economic framework
Sub-Category: European institutions' position on RES
Affected Technologies:
Biofuels
RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T other biofuels
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The increasing use of maize for producing first-generation biofuels (‘mazification’) has led to the public debate and occasional public protests against the cultivation and use of crops for energy purposes. The major issues are land and environmental impact of energy crops as well as the impact on food prices (‘tank oder teller’ debate).

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Transport
Code: DET52
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Biofuels
RES-T liquid biofuels (bio-LNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Electricity
RES-T electricity
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There is a lack of the properly developed public infrastructure of charging stations for electric cars. According to the official estimates Germany needs 36.000 normal public charging stations and 7.000 fast public charging stations for electric cars by 2020 to meet its needs. Currently, there are only 6.500 normal and 230 fast charging stations. Germany also almost entirely lacks the charging stations for LNG vehicles. The policy instruments and financial means for addressing this problem have been adopted.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Transport
Code: DET54
Category: Grid regulation and infrastructure
Sub-Category: Lack of infrastructure and infrastructure development
Affected Technologies:
Electricity
RES-T electricity
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Despite the financial incentives, the public perception and demand for electric cars, particularly by private persons, is still below expectations. This is due to the lack of infrastructure, shorter ranges and still higher prices of electric cars compared to conventional ones. The widespread image of the traditional cars as a status symbol in Germany also contributes to the lack of interest for electric cars.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Transport
Code: DET57
Category: Other
Sub-Category: Public perception of RES