Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In certain areas, access for new producers to the network is restricted, due to factors like poor infrastructure of the transmission and distribution electricity networks which is not adapted to connecting new facilities generating electricity. Furthermore, there is no guarantee of connection to the grid for RES, no priority connection of RES over conventional sources, technical restrictions introduced by companies involved in electricity distribution and transmission for those who apply for grid connection permits and finally speculators who are closing access to the network. After the publication in December 2015 of the Renewable Energy Sources Act (RES-Act) according to which the photovoltaic sector benefits from less complicated administrative and legal procedures than other RES, wind, biomass, biogas, water and geothermal sources lose in the race to grid access.

 

However, the new RES-Act introduced some positive changes. The grid operators are obliged to give electricity from renewable sources priority of transmission. However, they must apply objective rules to ensure equal treatment of all plant operators. The cost of connecting a plant to the grid shall be borne by the plant operator. Plants that generate electricity from renewable energy sources whose capacity does not exceed 5 MW are subject to reduced connection charges. The connection of micro-installations is free of charge.

 

Nevertheless, according to the RES-Act and new EU RES Directive, the obligation of purchase of electric energy concerns only installations with a capacity up to 500 kW. The grid operators have already started to renegotiate agreements, which creates a threat for the owners of renewable energy installations.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: PLE01
Category: Grid regulation and infrastructure
Sub-Category: Predictability / transparency of connection procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The amendment to the Energy Law Act of 8 January 2010 implemented an obligation to make an advance payment for the connection fee of PLN 30 (€ 7) for each kW of electric power of the facility to be connected. As specified in the provisions of the Energy Law Act, the advance payment is repayable by the electricity network operator/distributor when the grid connection permit is refused due to technical or economic conditions of the connection. The advance payment will also be refunded if the source is not connected. This is not provided in the statutory regulations. There is a risk that the entity may receive connection conditions which are not favourable to project implementation from an economic viewpoint.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: PLE02
Category: Grid regulation and infrastructure
Sub-Category: Cost of RES grid access
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

When connecting to the grid, the Distribution System Operator may establish a fee, which is agreed with the applicant. The connection of RES to the grid can be refused because of technical conditions at the time requested by investor.

Another problem is that for facilities above 2 MW a study on the impact of the connected generation facility on the electricity system is required, which results are inaccessible to applicants. Furthermore, distribution and transmission system operators include in the fee the cost of network modernisation and expansion outside the connection point.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged and addressed
Sector(s): Electricity
Code: PLE03
Category: Grid regulation and infrastructure
Sub-Category: Cost of RES grid access
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Most investments in renewable energy sources may be located in specific locations on the basis of the local spatial development plan. If municipalities did not develop their local plans, the development of the projects takes much longer (at least 1 year and up to even 3 years longer). There is also a lack of knowledge about the areas with possible grid connection capacities. These two factors increase enormously the risk on the side of the developer.

In order to obtain such documentation, it is often necessary to obtain a prior environmental decision which often is preceded by an environmental impact assessment of the planned project and a report on environmental impact assessment.

 

A location decision is required when applying for connection conditions to the electricity network. Thus, the investor is exposed to major risk of preparing a project without being guaranteed connection to the network but also without having information if, when and under what conditions such connection to the network can be made. Pursuant to art. 7 of the Energy Law Act, network operators/distributors are obliged to publish information on available capacity but only with respect to the network above 110 kV. This is, however, a dead letter as a majority of RES generation capacity in Poland is connected to the network with voltage up to 110 kV in total (according to the Polish Economic Chamber of Renewable and Distributed Energy (PIGEOR), this is the case for about 90% of all existing RES facilities).

 

Additionally, the existing provision of art. 7.8l of the Energy Law Act causes different interpretation, which results in diverging information on the websites of energy companies involved in power transmission or distribution. As a result, it is impossible to obtain clear information on the planned locations of physical connection of generation facilities (information is published solely for designated network voltage). This notwithstanding, a majority of TSO/DSO do not fully comply or do not comply altogether with the requirements of the Act with respect to providing information on grid connection capacity and on extension plans for the designated voltage range above 110 kV. There are also instances when the published information does not provide anything required by the legislator – no information is published on the available connection capacity at the connection point; only information on capacity available to end users connected to the network is published. Most TSO/DSO companies avoid the presentation of zero connection capacity.

 

Furthermore, a new project of the law on building is considered, which would introduce the condition that installations with capacity over 50 kW should be included not only in the communal plans of spacial development but also in the regional (wojewódzkie) plans.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE04
Category: Administrative processes
Sub-Category: Integration of RES in spatial and environmental planning
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The time required to develop fully permitted projects (with construction permit) is at least 9-12 months. Unfortunately, developers often inform about delays on almost every step of the project development. The most complicated administrative issues are the lack of spatial plans, the lack of information on available grid capacities, and difficulties while preparing environmental reports. In addition, the unstable legal situation (lack of fully implemented Directive 2009/28/EU) makes the project developing process much longer.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE06
Category: Administrative processes
Sub-Category: Duration of administrative procedure
Affected Technologies:
Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The legal system provides for using biogas not only for direct generation of electricity and/or heat, but also for a possibility to evacuate biogas into the gas distribution network. However in spite of the provisions of the RES-Act, the executive order regarding evacuating biomathane into the gas distribution network has still not been issued. The lack of additional executive order provisions still blocks the possibility of launching such installations.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE07
Category: Grid regulation and infrastructure
Sub-Category: Injection of biogas into natural gas grid
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The circles supporting the development of renewable energy sources in Poland have been waiting for years for Poland’s Government to propose and have an act approved on renewable energy sources that will set forth a long-term stable development of the energy sector and will introduce a basic legal order, in particular with reference to a long-term support strategy for the existing and planned installations using renewable energy sources. Past changes of the Energy Act did not convince the parties interested in RES development. After its adoption in February 2015, the RES Act has already been amended several times and next amendments are still due. The amendments have thoroughly changed the auction system, so that it supports more biomass and solar energy. Plans for auctions are announced always until the end of October of the previous year, so the system is not predictable.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE08
Category: Political and economic framework
Sub-Category: Reliability of general RES strategy
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The certificate-based support system (for installations connected before 1 July 2016) was changed and amended several times. The market price of the so-called “green certificates” observed slumps from almost 200 PLN/MWh (€ 46.50) in 2013 to around 100 PLN/MWh (€ 23.25) in May 2016 and 40 PLN/MWh in August 2016, after which it has remained at a comparable, low level, to recover in 2018. Part of the problem was the increased supply because coal-biomass co-firing is counted as green energy. The producers have also a big amount of certificates that has not been written off yet. On the other hand, the demand decreased significantly because of the change of required amount of certificates. It was changed from 15% of green certificates to 14.35% for green certificates and 0.65% for blue certificates (for biogas) in the second half of 2016. The situation was and partly still is particularly precarious for wind farms, which were financed predominantly by commercial loans.

 

The quota system was substituted by auctions (tenders) for installations connected after 1 July 2016 as well as for older installations wishing to move to the new system ("migration auctions"). The first auctions were carried out in December 2016 with just two more rounds in 2017. The long notification process, which due to a back-and-forth with the COM lasted nearly a year and a half, delayed further auctions. 13 rounds were carried out in 2018. However, there is no long-term scheduling of the volumes of electricity or shares of particular technologies. Despite the flaws of the quota system, many existing power plants did not migrate to the new auction-based feed-in premium support scheme due to the uncertainties (many such migration auctions ended unresolved).

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Policy Recommendation: Tender timetables

The RES Act should allow MoE executive orders with timetables, volume and reference prices for each technology.

Sector(s): Electricity
Code: PLE10
Category: Political and economic framework
Sub-Category: Reliability of RES support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There is no strategic support for the development of RES in Poland among politicians, state-owned energy companies and governmental bodies. Large parts of the ruling Law & Justice party and its administration oppose RES for various reasons. Firstly, some do not understand the necessity to begin a transformation of the power system that has functioned properly for years. Secondly, many are still under the infuence of the coal lobby.

The arguments used against RES are that the energy generated from such sources is more expensive and contributes to growing energy prices for end users, that it deteriorates the landscape and that it adversely affects the functioning of the electricity transmission system. These arguments and many others are used to minimise RES popularity among citizens. As a result, private investors struggle with an unfriendly investment climate. In this regard, the campaign against wind energy installations was particularly tough and resulted in the adoption of the new law on investment in wind plants, which makes such investments practically impossible.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE11
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The government declares clearly that coal will be the basis of the Polish energy system well into 2040s. Some measures taken by the government are aiming at hindering sustainable, renewable energy development (e.g. change of support for prosumers and restrictions for building wind farms). State-owned energy companies implemented the strategy which is based on co-firing of biomass (often from abroad) together with coal. New renewable projects like wind farms and biogas plants cannot be rival for such a technology, even if state-owned subsidiaries engage in RES projects and show great interest in offshore wind (esp. PGE). Therefore, enormous inequalities take place on the market.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE12
Category: Political and economic framework
Sub-Category: Reliability of general RES strategy
Affected Technologies:
Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

For several years, the companies investing in agricultural biogas plants have been voicing an unsolved problem related to excessively restrictive legal regulations concerning the use of fermented mass from agricultural materials and of agricultural origin directly in fertilising without the need to monitor heavy metal content as it is necessary in the case of sludge. Post-fermentation mass from agricultural biogas plants is treated equally in terms of legal approach as the sludge mass and thus it may not be used directly for fertilisation. The situation is not understandable as the sludge maybe used directly for fertilisation before the process of methane fermentation. After the methane fermentation process, the mass becomes a waste.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE14
Category: Political and economic framework
Sub-Category: Remuneration level for RES
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Banks make the financing of RES projects more difficult because of growing investment risks and lack of knowledge necessary to assess a project's viability. Many investors may have problems with paying off loans after the fall of prices of green certificates. Under the new auction system, the entire risk is on the side of the investor (and not of the government), so many banks become even more reluctant. The unstable, constantly amended legal framework further exacerbates the reluctance of financial institutions to back up investment in RES. The Polish Banks Association voiced its concerns and in February 2018 called on the government to approach RES wholistically and seriously.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE15
Category: Political and economic framework
Sub-Category: Access to finance
Affected Technologies:
Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The current support system is not sufficient for PV and biogas installations with a capacity of approx. 100 kW to 2 MW. Although the new system includes different reference prices for different technologies (whereas the previous support scheme had only one reference price), the current support still does not ensure viability of small PV and biogas projects (according to a PV expert).

The insufficient national support scheme for PV and biogas installations may however be counterbalanced in some regions, where enterprises, cooperatives and housing associations might obtain a subsidy of up to 85% of the value of the investment.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE16
Category: Political and economic framework
Sub-Category: Remuneration level for RES
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In some places there is opposition against RES installations from associations which can act as a part of procedure (environmental planning and building procedure). The protests resulted in the adoption of the new law on investment in wind plants, which makes such investment practically impossible.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Policy Recommendation: Empowering municipal administration

Given the current "anti-wind law," the development of wind energy has been brought to a halt. This could be helped by giving the decision-making power to municipalities (e.g. communes) to rule on RES projects themselves, including e.g. referenda.

Sector(s): Electricity
Code: PLE19
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The grid capacity is not sufficient, and DSOs seem to make progress only at a sluggish pace. In 2017, 76% of overhead high-voltage (110 kV) lines of five biggest DSOs were older than 25 years.

Component Authority:  DSOs
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE20
Category: Grid regulation and infrastructure
Sub-Category: Lack of infrastructure and infrastructure development
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Coal is the major source of energy in Poland. Large state-owned facilities and grid companies dictate their terms on the market and thus leave only very little leeway for stakeholders of the renewable energy sector.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE21
Category: Market structure
Sub-Category: Dominance of conventional retailers
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In Poland, a high amount of the suitable land plots for renewable energy installations belongs to the Agricultural Property Agency (Agencja Nieruchomości Rolnych). However, the administrative procedure for the use of those land plots is unclear, complicated, expensive and time consuming. There are clear limitations for RES installations within city limits and changing land status, which is related to spatial planning difficulties at municipal level.

Component Authority:  Agencja Nieruchomości Rolnych
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE23
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There is a constant preference and promotion of conventional and nuclear energy by the Polish Government. Renewable energies are still considered as ineffective and expensive technologies. There is a strong preference for centralised solutions of the energy system, despite recent interest of PGE in offshore wind. Moreover, RES are viewed as destabilising the system.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE24
Category: Market structure
Sub-Category: Fair and independent regulation of the RES sector
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The process of obtaining environmental decision for large projects, i.e. wind farms, is complicated, due to the fact that such projects involve administrative decisions touching upon both the project itself and the transmission grid. Because of the file complexity of large projects connected to the transmission grid, the whole permitting procedure is long and complicated for the administrative authorities.

Component Authority:  Ministerstwo Środowiska
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE26
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

At each step of the procedure, residents may repeal from the decision (i.e. environmental decision, building plan) without stating an exact reason. This is why the repeal procedure can last forever. Also, the reasons to repeal can be unjustified, they still have to be taken under consideration of the proper authority. However, according to the RES-Act, in some cases the repeal has to be considered within a maxiumum of 30 days.

Component Authority:  Municipalities
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE27
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Different tax rates for the turbine constructions and for the farm infrastructure, as well as for ground-mounted and on-roof PV installations. Legal changes are a work in progress.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE28
Category: Other
Sub-Category: Taxing regime
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Transmission lines from the wind farm usually have to go through allotments owned by private landowners. This frequent situation results in high costs of the remuneration for the landowners for the use of the land. Such a situation makes the investment much more expensive and time-consuming, esp. concerning the negotiation process.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE29
Category: Grid regulation and infrastructure
Sub-Category: Cost of RES grid access
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In June 2016, the Polish Parliament adopted a new law on investment in wind plants. The law aims at protecting health and maintaining the standard of living of the citizens in the vicinity of wind farms. The new provisions make it illegal for new wind turbines to be located near homes, schools and natural reserves. In general, the construction of wind turbines will be not allowed at a distance of at least 10 times their height, that is around 1.5 km. According to the wind power industry, this solution will practically stop the development of wind onshore energy in Poland.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE31
Category: Market structure
Sub-Category: Fair and independent regulation of the RES sector
Affected Technologies:
Biomass
RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The Polish State Forests abuse its dominant position on the biomass market as a nigh on monopsony. Limiting supply, the company can avoid biomass price decreases. This leads to forest biomass being artificially more expensive than it could be, especially given limited imports, also in the light of low use of agricultural biomass.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE33
Category: Market structure
Sub-Category: Fair and independent regulation of the RES sector
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Previously, there was competition for clients even among state-owned companies. Currently, there is less focus on competition and an observable tendency of executing government policy. This is clearly seen on the example of extending statutory activities beyond purely commercial to ensure energy security. Such developments create uncertainty as to dynamic competition and undermine the credibility of price formation by the so-called fundamentals. In addition, this leads to the fact that investors look more to government for price floors rather than price/cost analytics.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE34
Category: Market structure
Sub-Category: Dominance of conventional retailers
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The role of grid operators in the development of renewable energy sources is underestimated. There is a need for a clear signal from the government to grid operators as to the direction of energy policy. Otherwise, they will remain uncertain about investments in expanding the network for (future) decentralised energy, research, smart grid projects etc.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE35
Category: Grid regulation and infrastructure
Sub-Category: Transparent and foreseeable grid development
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The Energy regulatory office has no uniform criteria for admission to tenders. There is no closed catalogue of criteria for this purpose, which leads to discretionary decisions and very similar, individual cases being dealt with very differently. In addition, the 30-day deadline for decision is often not met.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE36
Category: Administrative processes
Sub-Category: Complexity of administrative procedure
Affected Technologies:
Solar power
RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Sometime PV plants have a poor quality of components or suffer from a poor quality of installation, thus increasing fire risk. As a consequence, some installers have seen their licence revoked. There is still no clarity as to the fire protection regulations for rooftop PV systems. PV systems are still not bound by the final inspection norm IEC 62446. The consultation process on how to change the current state of affairs is ongoing.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE37
Category: Other
Sub-Category: Certification
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

In August 2017, the Renewable Energy Sources Act was amended to set the substitution fee for surrendering green certificates at 125% of the average certificate price from the year before (but no more than 300.03 zł/MWh, approx. € 72). The cap is fixed at the previous level of the substitution fee. Given low certificate prices, the amendment is highly disadvantegous for RES installation operators and benefits state-owned utilities.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE38
Category: Political and economic framework
Sub-Category: Reliability of RES support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Auctions are a barrier for many smaller installations due to the administrative complexity and length of procedure and the effect of economies of scale of larger generators with larger portfolios and an optimised cost structure. This is especially true given the lack of a published tender timetable with volume per technology.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE39
Category: Political and economic framework
Sub-Category: Existence of RES support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

RES investors overly concentrate on the viability of individual business cases while neglecting system stability issues. As a result, there is a lot of mistrust between the community of investors and DSOs/TSO. At the same time, investors and their association have so far failed to underline the systemic benefits of RES, e.g. increasing energy security and security of supply (esp. PV's contribution to cover summer load peaks).

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Electricity
Code: PLE40
Category: Other
Sub-Category: Information exchange / communication between relevant stakeholders
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E offshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E large hydro (> 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Ocean energy
RES-E wave energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E tidal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Poland exhibits an insufficiency of centres and institutes dealing with the topic of modern electricity systems. As a result, the discourse on the energy transition is lagging behind and finds its ways into the legislative debate and legislation itself with delays.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Electricity
Code: PLE41
Category: Other
Sub-Category: Information exchange / communication between relevant stakeholders
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Geothermal energy
RES-E geothermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Some investors bid too low counting on the falling of investment cost. Morover, especially in the wind farm industry, due to the unfavourable legal environment and the lack of serious tenders in recent years, investors are ready to take more risk, to have any chance of implementing their projects before the expiry of connection conditions or building permit decisions, which they could no longer extend due to the so-called 10H distance regulation. Others yet develop RES installations with the intention of selling. As a result, many tender-winning projects are never implemented, thus squandering the chance of tapping the full potential of RES development. The amount of the penalty at the time – loss of deposit of 30,000 PLN/MW (7,000 EUR/MW) – for non-generation of contracted electricity volume and ban from future participation in tenders – proved insufficient. Based on the information from the Energy Regulatory Office (URE) many projects to win the first RES tender for installations up to 1 MW of late 2016 have failed to be implemented. Only 1 out of 11 wind farms and only 55 out of 73 PV projects have seen completion.

Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Policy Recommendation: Safeguards against underbidding

Increase sanctions for non-implementation of a tender-winning project. Firstly higher penalty for non-generation of the contracted electiricty volumes. Secondly, since many projects enter the tender as a special-purpose vehicle, banning them from future participation in tenders is unenforceable – this should be solved. Another solution would be higher deposits per 1MW, however, this should be weighted against the fact that it could prove prohibitive to some projects entering tenders.

Sector(s): Electricity
Code: PLE42
Category: Political and economic framework
Sub-Category: Reliability of RES support scheme
Affected Technologies:
Wind power
RES-E onshore wind
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solar power
RES-E PV ground-mounted
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E PV rooftop
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydro power
RES-E small hydro (≤ 20 MW)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-E gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-E solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Despite the Ministry's attempts to establish basic standards for energy clusters through certification competitions (only two so far), these had no legal basis and the energy clusters' evaluation was carried out in an intransparent and arbitrary manner, allowing no appeals at any stage. Support is offered for energy cluster projects for which viable business models cannot be developed based on the cluster format.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Policy Recommendation: Drafting a "distributed energy act"

It is necessary to elaborate and publish at least the draft assumptions for the distributed energy act, as announced in 2017. Local balancing zones are able to bring tangible benefits even without subsidies or competitions but require above all a stable and friendly regulatory environment and no direct interference in their development on the part of public institutions. The Ministry of Energy should focus on system solutions.

Sector(s): Electricity
Code: PLE43
Category: Political and economic framework
Sub-Category: Reliability of general RES strategy
Affected Technologies:
Biomass
RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The introduction of green certificates to support producers of electricity from renewable energy sources (RES) has resulted in the transfer of a significant part of biomass supply from the heat production industry to the electricity sector. Consequently, there has been no significant increase in the share of primary energy in domestic biomass in recent years. Effectively, there are anomalies in the use of biomass for heating purposes. Energy companies, guided by a potential profit derived from green certificates, obtain biomass for blocks generating electricity. A major part of RES electricity generated in Poland is produced from biomass, particularly in installations for co-firing of biomass with coal and from large installations for biomass. Thus, availability of solid biomass for heating purposes at a reasonable price for the heating sector is very much limited.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: PLHC16
Category: Other
Sub-Category: Lack of resources for natural and economic reasons
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

The government and the stakeholders have not developed a common vision and targets for the heating and cooling sector. Targets exist only for CHP, but officially there is no mention of fuel mix or emission performance standards, neither for integrated heating systems nor for individual systems. Without clear targets it is difficult to communicate the necessity of action and to choose the right policies and tools.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: PLHC22
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Municipal governance is responsible only for the creation of general objectives regarding the sources of heat generation but not for the development of concrete plans and strategies for the heating sector in its entirety. Without a clear green light given at national level, local solutions including RES-HC, are impeded.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: PLHC23
Category: Political and economic framework
Sub-Category: Reliability of general RES strategy
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Large public aid is being used, first and foremost to deploy newest (5th class) coal-burning boilers, with a total budget of PLN 103 billion (€ 24 bn). This, however, distracts effort. This creates a lock-in effect and impedes the development of RES-HC.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: PLHC24
Category: Political and economic framework
Sub-Category: Existence of general RES strategy
Affected Technologies:
Geothermal energy
RES-HC deep geothermal
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC shallow geothermal (heat pumps)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Average returns in all of the H&C sector amount to merely 2%. Since RES-HC installations requires upgrades and integration with new systems, many boilers have to be modernised. However, investors and households are particularly reluctant to invest in such refurbishment works, given the regulator's discretionary and often arbitrary approach regarding qualified costs. The Ministry is aware of the problem, however no significant measure was taken to overcome this issue so far.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Acknowledged
Sector(s): Heating and Cooling
Code: PLHC26
Category: Political and economic framework
Sub-Category: Remuneration level for RES
Affected Technologies:
Solarthermal energy
RES-HC solarthermal energy
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Biomass
RES-HC gaseous biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC liquid biomass
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (waste)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-HC solid biomass (forest by-products)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

Geothermal energy is used as an excuse for government action in the RES-HC field. However, geothermal energy is a viable solution for only a dozen or two heating systems while solutions are needed for about 400 systems nationwide.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Heating and Cooling
Code: PLHC5
Category: Political and economic framework
Sub-Category: Reliability of general RES strategy
Affected Technologies:
Biofuels
RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T other biofuels
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydrogen
RES-T hydrogen
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There is no interest in and knowledge of the RES use in transport neither in the society nor among the politicians.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Transport
Code: PLT32
Category: Other
Sub-Category: Public perception of RES
Affected Technologies:
Biofuels
RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T other biofuels
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There are too strong quality requirements towards biofuels, which are not scientifically grounded. This obstacle concerns both first and second generation biofuels. For the first generation biofuels, including biodiesel comprising Fatty Acid Methyl Esters (FAME), there is a problem in complying with the parameter of resistance to oxidation measured by the so-called Rancimat method. Because of the relatively rapid oxidation of FAME in the conditions of distribution and storage and with no clearly examined impact of the catalytic construction materials (particularly those containing copper), biodiesel producers are forced to substantially increase the oxidation resistance through the introduction of greater amounts of antioxidants. These however, have influence on the aging process of the fuel. Planned requirements for advanced biofuels do not have any confirmation resulting from research or practice and will hinder the introduction of "drop in biofuels" in Poland.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Transport
Code: PLT34
Category: Political and economic framework
Sub-Category: European institutions' position on RES
Affected Technologies:
Biofuels
RES-T gaseous biofuels (biomethane)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T gaseous biofuels (bio-CNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (biodiesel)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bioethanol)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T liquid biofuels (bio-LNG)
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

RES-T other biofuels
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Electricity
RES-T electricity
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Hydrogen
RES-T hydrogen
Spread
  1. The barrier impacts sporadically on installations of the above mentioned technologies.
  2. The barrier affects a small fraction of installations of the above mentioned technologies.
  3. The barrier affects a moderate share of installations of the above mentioned technologies.
  4. The barrier affects a predominant share of installations of the above mentioned technologies.
  5. The barrier concerns almost all installations of the above mentioned technologies.
Severity
  1. The identified barrier has minimal effects on the further development of installations of the above mentioned technologies. It causes no or negligible time loss and has no or negligible financial consequences.
  2. The barrier has minor effects on the further development of installations of the above mentioned technologies. The completion of the installation may be slightly slowed down and financial consequences may (rarely) arise.
  3. The barrier has moderate effects on the further development of installations of the above mentioned technologies, resulting into important time and financial losses.
  4. The barrier has substantial effects on the further development of installations of the above mentioned technologies. The completion of the installation could be seriously jeopardized, resulting into substantial time and financial losses.
  5. The identified barrier has severe effects on the development of installations of the above mentioned technologies, leading to project abortion.

Description:

There is no vision for the development of the sector.

 

The strong state support for the development of electric cars and the goals for usage of electric cars announced in the Plan for Responsible Development are not combined with increased production of electric energy from renewable energy sources. New technologies in biofuels production are not supported.

Component Authority:  Ministerstwo Energii
Barrier Acknowledgement:  

Acknowledged and addressed - The barrier has been acknowledged by the competent authority and some measures were officially undertaken to overcome it. However no positive effects could be observed yet.

Acknowledged - The barrier has been acknowledged by the competent authority. However, the policy makers and stakeholders competent to overcome the barrier have not addressed the problem so far.

Not acknowledged - The barrier has not been acknowledged by the competent authority. As a result, no measures were undertaken.

Not acknowledged
Sector(s): Transport
Code: PLT35
Category: Political and economic framework
Sub-Category: Existence of general RES strategy